Construction update – March 2026
News18.04.2026

March across our construction sites – the sunshine is helping work move forward!
Zielone Rabowice 3 E3.5:
- façade works have been completed,
- heat pump installation is underway,
- interior finishing works are underway,
- driveway and terrace works are underway.
Zielone Rabowice 3 E3.6:
- masonry works are underway.
Barwne E2:
- loft structure works have been completed,
- window and door installation is underway,
- façade works are underway,
- electrical installation works are underway,
- internal plastering works are underway,
- water, sewerage and central heating installation works are underway.
Botanika Pobiedziska E2:
- electrical installation works are underway,
- internal plastering works are underway,
- water, sewerage and central heating installation works are underway,
- façade works are underway.
More posts
Zobacz wszystkieContact us!
Do you have questions about our developments, are you looking for the right property or would you like to discuss working with us? Complete the form or use the contact details below.
Greenbud Development
ul. Dworcowa 4
62-020 Swarzędz
Privacy policyCopyright © 2026 Greenbud