Construction update – April 2025
News08.05.2025

Let’s take a look at what’s happening across our developments!
Nowy Jasin E3.4
- façade works completed
- finishing works underway
Zielone Rabowice 2 E7.5:
- all homes have been handed over to their owners
Zielone Rabowice 2 E7.6:
- window installation completed
- central heating installation works underway
- internal plastering works underway
- electrical works underway
Zielone Rabowice 3 E3.4
- internal plastering works nearing completion
- façade works underway
- electrical works nearing completion
Zielone Rabowice 3 E3.5
- masonry works underway
Botanika Pobiedziska E1:
- 8 out of 10 homes have been handed over to their new owners
Botanika Pobiedziska E2:
- construction works have begun
- building setting-out completed
- topsoil removed
More posts
Zobacz wszystkieContact us!
Do you have questions about our developments, are you looking for the right property or would you like to discuss working with us? Complete the form or use the contact details below.
Greenbud Development
ul. Dworcowa 4
62-020 Swarzędz
Privacy policyCopyright © 2026 Greenbud